Recording time against Programs and Portfolios - any work arounds?

Avatar

Level 3
 
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Community Advisor

Hi Jim,

Since time can only be entered against Projects, Tasks, Issues, or as General Time, you could model one of those levels to represent each Portfolio / Program, such as:

  • create a General Time entry for each unique Portfolio and each Portfolio / Program of interest
  • create one Project for each Portfolio for Portfolio Time, and one Task for every Program for Program Time
  • create a Project to house all such time, with one Task for each Portfolio for Portfolio Time, and one Issue for every Program for Program Time

Regards,

Doug

Thanks Doug. Good ideas.