Hi @Vic Alejandro That is the approach we have been taking, but we ask creative to log time per task, assign them a cost per hour within their account and set User Hourly as the cost type. So, the cost of their work rolls a planned/expected cost into the projects. According to the "
https://support.workfront.com/hc/en-us/articles/217300507-Tracking-Costs">Tracking Costs article though, WF tracks project costs as Labor Costs (what we are calculating through hours logged, assigned cost per hour, etc) + expense costs. My concern is that if we log freelance invoices as planned/actual expenses and WF is already assigning a cost to that freelance work, our project financial data includes duplicated data Catherine Hayes The Channel Company