Hi - I have an agile team configure Kanban with tasks assigned to the team's backlog. When a team member moves an task to the "In Progress" column, the item disappears from the board. If I navigate to the task within the project it shows as "In Progress". The team member did not have an right assigned to the project at the time. Once I gave the team member "Manage" access, they were able to move the tasks with the expected behaviour. Any ideas...?
Topics
Topics help categorize Community content and increase your ability to discover relevant content.
Old discussion, but I'm finding the same in a Kanban board when items are moved to Complete - they disappear. Any resolution to this? I'm opening a support ticket now. Greg Troester CHG Healthcare Services, Inc.