Priority level be tied to dates on template?

Avatar

Level 1
Hello, I was wondering if it is possible when you are creating a project from a template and you choose the priority to the project, can the priority be used to determine the length of the project? or will I have to create multiple templates for the one type of project with different lengths. For example; low/medium/high priority all have the same template but will have different applied dates. Thank you, Lucas Wilcox Sunrun Inc.
1 Reply

Avatar

Level 8
Dear Lucas, You would need multiple templates. Once a template is applied (like it is when you create the project for example) it is not a dynamic object. The tasks after that point would need to be manually updated. Barry Buchanan Work Management Australia