Hi all, This may be a case of trying to do too much with too little, but I'm desperate to rid myself and my team of a manual process. Here's the situation: As the PMO, we are responsible for tracking and managing the budget related to any contracted PM work our projects are using. Basically, we contract a specific resource to manage a specific project and the SOW covers a specific dollar amount. Our dilemma: Currently, these contracted resources track their time in WF (win!), but each week we manually move their hours over to a spreadsheet. The spreadsheet mainly tracks hours per week, budget used per week, and budget remaining. Solution we are trying to get to: Since the hours are already tracked in WF, my team thought we could craft a solution in WF that would eliminate our manual intervention. Ideally we would be able to monitor some reports instead of entering on spreadsheets. Solution Hurdles: (1) I can't find a way to multiply the user's hours logged weekly against the user's billing rate (I suspect I can do it in a calculated column, but I can't get the text mode to work). (2) I can't find a way to calculate the remaining budget based on hours logged by the user on that specific project at that users bill rate. As always, I am grateful for any input/help from WF experts out there! Alison Angilletta PMP Director, PMO RWJBarnabas Health