Looking to create some special reports

Avatar

Level 1

Looking to create a report that displays hours recorded by worker for a specific week. I am also looking to create a report that displays time recorded to each individual task by project.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Community Advisor

Hi Tedd,

I'd suggest you start with an Hours matrix report grouped by Hour Owner (vertical) and Entry Date (horizontal, by day) filtered (or prompted) within a specific week, then copy that report and instead group by Project Task on the vertical, rather than Hour Owner.

Regards,

Doug

Avatar

Level 1

Thanks Doug. I'll give that a try.