I want to compare planned VS actual hours on our project templates. Is there a built-in way?

Avatar

Level 3
I want to compare planned VS actual hours on our project templates. Is there a built-in way?
2 Replies

Avatar

Level 7
We create a top-level roll-up task for all our projects and on the task view, show planned hours and actual so they all roll-up to the top level task so we compare that way.

Avatar

Level 10
Hi Michelle, There is a field called 'Planned Hours Alignment' which you can add to a Project view or report. This is also available for Task reports/views. Regards, David