How does WorkFront determine task and project conditions (automatically)?
I know how to edit the task and project conditions manually, but to do it automatically, does the system use planned vs. projected completion dates or something?
Eric - there are great explanations of this in the HELP area. See "https://support.workfront.com/hc/en-us/articles/216636328-Understanding-Progress-Status-of-Tasks" Understanding progress status of tasks and "https://support.workfront.com/hc/en-us/articles/217239547#understanding-project-condition" Understanding Project Condition for the details. In essence, it has to do with the planned vs. projected dates.