Expand my Community achievements bar.

How do I modify baselines?

Avatar

Level 10
We've always had enabled the "Create baselines automatically" option in Setup which does so when a request form is converted into a physical project. Our main approval however comes a few weeks after that conversion occurs, and which historically we've not been snapping baselines for. I have a list of finish dates from these approvals and I'd hoped I could create some baselines and then straight after manually enter in the Planned Completion Date etc. as of the time of these approvals, but from the interface it looks like it can't be done. Is there a way around this? Jamie Hill JLL Global
2 Replies

Avatar

Level 10
I am not aware of any way to modify the contents of a baseline. They are locked and read-only as far as I've been able to determine. Eric

Avatar

Level 10
Thanks Eric. I thought this might be the case! Jamie Hill JLL Global