Hello! Is there anyway I can change the date a task was completed on? For example if the task was sent to the client, and it was marked complete on 10/3, but was actually completed on 9/22, can I go back and change the date to show that it was completed on the 22nd? Thanks, Saher Almaita
2 Replies

Avatar

Level 5
Found the solution in another thread.. It can be edited in the Detail Overview for the project... Next question how do I delete Discussion posts?? Thanks, Saher Almaita

Avatar

Level 10
You can also display that in one of your Views on your project so you can see it in the line item and you can edit it right in line. May save time of having to go into Detail Overview for each task. We actually have a View/Report for Completed tasks that has the Actual Completion Date and Planned Completion Date. Then in my weekly update of the plan I sync them to be the same by changing the Planned Completion Date in-line to reflect the Actual.