In a Project Report, I am trying to calculate the difference between the Default Baseline Planned Completion Date and the Project Projected Completion Date. It is always returning null (blank on the report. Does anyone have a solution? Thank you. This is my text: displayname=Variance name=Variance textmode=true valueexpression=FLOOR(DATEDIFF({defaultBaseline:plannedCompletionDate} , {projectedCompletionDate}),2) valueformat= Steve Theobald PMP
2 Replies

Avatar

Level 10
Try displayname=Variance name=Variance textmode=true valueexpression=FLOOR(DATEDIFF({defaultBaseline }.{ plannedCompletionDate} , {projectedCompletionDate}),2) valueformat= Polly Co

Avatar

Level 3
Thank you!! That worked. :) Steve Theobald PMP OH-DAS