I'm working on a task report and want to create a calculated column for the days difference between the Projected Completion Date of the Predecessor and the Planned Start Date of the dependent task. A negative number would obviously mean the predecessor is going to run later than the dependent Task's Planned Start Date. Am I on the right track? Thanks
displayname=Slip Days textmode=true valueexpression=WEEKDAYDIFF({actualCompletionDate},{predecessor:plannedStartDate})