Calculated Column between Predecessor & dependent Task dates

Avatar

Level 4
Hello, I'm working on a task report and want to create a calculated column for the days difference between the Projected Completion Date of the Predecessor and the Planned Start Date of the dependent task. A negative number would obviously mean the predecessor is going to run later than the dependent Task's Planned Start Date. Am I on the right track? Thanks displayname=Slip Days textmode=true valueexpression=WEEKDAYDIFF({actualCompletionDate},{predecessor:plannedStartDate}) Andrew Beard Sr. Associate, LeapPoint "mailto:abeard@leappoint.com" abeard@leappoint.com 203-232-4090
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 10
Andrew, I'm struggling with this as well. Try re-posting this question to the global discussion board. Benetta Perry APS