When you snap a baseline, does that baseline include assignments? I think, but would like to verify, that the baseline ONLY includes project-level and task-level information, NOT assignment-level information. What do you think?
Thanks!
Eric
I don't think so either. When you go to create a Baseline Report, and look at all the fields in the Baseline table, there's nothing there for assignments.