Baselines - creating automatically

Avatar

Level 6
Hi Is there a way to create baselines automatically? It would be nice to set them to create on set days, say end of the month or even as a project moves through a stage gate. Thanks
4 Replies

Avatar

Level 10
The only automatic one is when a project first goes from Planning into Current. An "original" baseline is created. Otherwise, you can't unless you use the API.

Avatar

Level 10
Hi Laura. Our Create Baseline solution lets you choose an Workfront Project Filter, and when run, a Baseline is created of each Project that matches the Workfront Filter. It is a schedulable, allowing it to automatically be run daily or weekly, or with advanced Filtering, by status period (e.g. bi-weekly, 1st and 16th, etc.). Regards, Doug

Please explain how to set the daily/  weekly setting baseline automatically