Backdate project actual completion in kickstart?

Avatar

Level 1
Is there a way to backdate project actual completion date in kickstart? When I try to import via kickstart it is setting acutal completion to today's date, despite filling in the columns setActualCompletionDate and setActualStartDate with the dates for setPlannedCompletionDate and setPlannedStartDate. The planned dates work fine, but the actuals only set to today. These are projects that were completed a while ago in another system and I would like to migrate them into Workfront.
1 Reply

Avatar

Level 5
Yep I hit this too. The trick is that the project completion date is when the last task completes. Set up another tab with one task per project and set the task's start and end date equal to the desired project start and end dates. Melinda Layten mlayten@gmail.com Independent Workfront Consultant