We have a project showing up in "My Work" from 2014. Want it to show complete and not show up in "My Work". The project shows complete, but it is still showing up in his "My Work" Is there a way to get this out of "My Work?" Becky Grosh Humana
1 Reply

Avatar

Level 10
There should be a little drop down to the right of your Task when viewing in My Work that allows you to remove it. Vic Alejandro, PMP, CSM | Senior IT Project Manager Denver Water | t: 303-628-7262 | c: 303-319-6473 Http://www.denverwater.org Sent via mobile phone