Agile - see attached. Can someone explain/help me understand why it shows "Completed Stories" 14 of 27 (there are 18 stories all completed)? Next why completed hours are 95.25 of 145 when it is 100% complete? The blue line shows 100% complete 87 is that hours? if so all of these are complete.
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 10
Hi Becky, The blue line is the ideal (required) burndown rate, not the actual burndown rate. The red line is the actual burndown rate. However, if you think the burndown chart data is not correct/up-to-date, then you can click (top-right) on 'Iteration Actions' then 'Synchronize Burndown Data'. Then reload your Storyboard and see if the data looks correct. Curious to know how you go, so please let us know! Regards, David p.s. In case you haven't yet had a look, there's good documentation at https://support.workfront.com/hc/en-us/articles/218008458-Using-the-Agile-Burndown-Chart