I was asked to create a report that showed all (or certain) projects in a portfolio with their Actual, Planned and Budgeted Hours. I built a view that would accomplish this. However, now the user would like to see hours just in the current year. We have projects that span multiple years and at times they want to just see numbers from this year.
A few of my thoughts
The filter feature doesn't work as I'm in the Project view and need to filter on Entry dates for Actual hours and estimates
To build a report, I would need to combine Resource Estimate, Task(?, for planning) and Hour report objects into one and filter each to limit to this year. Is this even possible?
The new Utilization report is good, but it only works on one project at a time, when we want to see the whole portfolio at a glance.
Thoughts, ideas?
Srini