Accounting for Office Closure/Holidays

Avatar

Level 2
Is there a way that I can set holidays in the system so that my project timeline calculations omit those days when calculating the timeline? Thank you. Maria Cortina Marketing Innovators International, Inc.
2 Replies

Avatar

Level 10
You can do it within system global setting. You just need to add exception within the Schedule you use :) Just click on it and it will open schedule settings for you. Dagmara Garwell BAKKAVOR LTD

Avatar

Level 2
Thanks so much! I'll give this a go! Maria Cortina Marketing Innovators International, Inc.