Expand my Community achievements bar.

The Community Ideas review for H1 2025 is out now, see which ideas our Product team prioritized and let us know your thoughts.

TASK and MUST FINISH BY DATE

Avatar

Level 5

8/31/17

When a product backlog item (PBI) is pulled into a sprint, a constraint of ‚ÄòMust Finish On’ is placed on the task and the start/end dates are changed to the end date of the sprint.

This is all fine if an item gets completed or moved to another sprint.

If a PBI was not completed and gets unassigned from a sprint, the constraint of “Must Finish On” remains as well as the date of the sprint and now the task is LATE.

The request is to put the “As soon as possible” constraint back on a task when it is removed from a sprint (Iteration->Name = blank) so that the task continues to ‚Äòflow’ with the project.