Similar to MS Project, ability to make a task inactive but leave it in the project to retain the history of the project.It would remove dependencies and impact of that task so it no longer affects the schedule or resources.

1 Comment

Avatar

Level 2

10/17/17

This would also be really helpful for tasks you know will be coming down the road but you have not yet figured out time timing and details for