We would like to see the Risk section updated to include a Consequence column added. Thus allowing the calculation of a risk score by multiplying the Probability and Consequence.

We would like to transition our excel based risk tool into Workfront.

3 Comments

Avatar

Level 3

3/19/24

We would definitely like to be able to add columns into the risk register that are editable (similar to the issues / tasks area). We have an excel spreadsheet that we would like to transfer over.

 

 

Avatar

Community Advisor

3/19/24

 

Hi @EmmaGr,

 

I invite you to consider (as many other customers do) setting up and using a special type of Issues, rather than Risks, to track your Risk Register, since the former supports Custom Forms in which you can then add such columns.

 