Adjusted Planned Start Date

  • April 20, 2017
  • 1 reply
  • 296 views

We would like a calculated field built into tasks that would display a New Planned Start Date that is based off of the Actual Completion Date of the Predecessor Task. For example, if Task 1 completes 2 days before the Planned Completion Date, then task 2 would have an Adjusted Start Date two days sooner than the Planned Start Date. It would be great if we could then make the My Work area go off of this, instead of just the Commit Date or the Planned Start Date.

1 reply

Level 6
April 15, 2019

Also, if a task is completed 2 days late, all tasks following should update their planned start date.