When changing a blueprint version of a page, how to rollout to en and affiliate blueprints so that the previous page is updated

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

If I understand your needs correctly, you want to broadcast the modifications from the blueprint version to the live copies. This can be accomplished by employing the "Rollout" operation (from the blueprint) and the "Synchronize" operation (from the live copies).

 

View solution in original post

2 Replies

Avatar

Correct answer by
Community Advisor

If I understand your needs correctly, you want to broadcast the modifications from the blueprint version to the live copies. This can be accomplished by employing the "Rollout" operation (from the blueprint) and the "Synchronize" operation (from the live copies).

 