Expand my Community achievements bar.

SOLVED

How to configure journey/WF to launch on a specific hour or time, not specific day, not using waves

Avatar

Level 2

Hello,

 

My team is looking for an option to launch newsletters in a specific hour, like when we launch the workflow, those Newsletters to launch at specific hour, like an schedule but we use schedule to program the whole WF, we are looking for a solution to send those Newsletters in separated hours in the same day when schedule starts.

 

Day 1 scheduled at 8 o clock of the morning, send NL 1 at 1+ hours, NL2 at 3+ hours (not using waves)...

 

Is that possible? what can we do to simulate this, or we have to create multiple WF with multiple schedule...

 

Thank you.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi @AdobeCampaignProxd ,

You can use Wait activity before Delivery activity.

In Wait activity, define how much hour/time you need to wait for the next activity to execute.

ParthaSarathy_1-1697530528412.png

ParthaSarathy_2-1697530947926.png

 

To know more about Wait Activity - Documentation

View solution in original post

3 Replies

Avatar

Correct answer by
Community Advisor

Hi @AdobeCampaignProxd ,

You can use Wait activity before Delivery activity.

In Wait activity, define how much hour/time you need to wait for the next activity to execute.

ParthaSarathy_1-1697530528412.png

ParthaSarathy_2-1697530947926.png

 

To know more about Wait Activity - Documentation

Avatar

Level 2

Thank you Partha, looks clean and simple, we are gonna test this solution 

 

Best regards.

Avatar

Administrator

Hi @AdobeCampaignProxd,

Was the given solution helpful to resolve your query or do you still need more help here? Do let us know.

Thanks!



Sukrity Wadhwa