Hello, I would like to know if there is a way to trigger a wkf based on another wkf with for example one week delay.
WKF1 starts at 19th december and when it is done the WKF2 starts automatically the 26th december.
I've tried using javascript and signal activity but the JS node keeps running until the 7 days passed and I guess it is not good and can create performance issues if scaled to several campaigns.
Another way is to create some logic with scheduler node but I was wondering if it is possible to achive this with signals.
Thanks