Situation: I set up a report in Adobe.  The way I set it up is to send a 90 day report to our team once a week (PDF).  After talking to the team, we decided it would be more beneficial to view a 7 day report once a week, and then a 90 day report once a month.

Question: Do you know how to modify the report sending?

Other info in case you need: The way I set up the report was: AAWorkspace/create report/share/send file on schedule/PDF/Frequency: Send weekly; Send every 1 week; SEND ON SCHEDULE... I inputted each person's email address into the box... Soooo, I don't know how to get back there to adjust the schedule.

1 Accepted Solution
Gigazelle
Correct answer by
Employee
Employee

Yes, Go to Components > Scheduled Projects. You can locate the project and adjust the schedule from there.

View solution in original post

0 Replies
Gigazelle
Correct answer by
Employee
Employee

Yes, Go to Components > Scheduled Projects. You can locate the project and adjust the schedule from there.

View solution in original post