Set minimum days - Date field Help

  • November 17, 2023
  • 2 replies
  • 602 views

We are getting project requests with unrealistic due dates.  Is there a way to "block" the due date (Date custom field) so people can't pick anything less than 2 weeks into the future for a due date?

Thanks!

Best answer by Madalyn_Destafney

Hi there, unfortunately there isn't that calendar blocking functionality you're looking for. Here are similar Ideas to upvote:
https://experienceleaguecommunities.adobe.com/t5/workfront-ideas/put-constraints-on-request-planned-completion-date/idi-p/519217 
https://experienceleaguecommunities.adobe.com/t5/workfront-ideas/enhance-date-field-in-custom-form/idi-p/530919 

2 replies

Madalyn_Destafney
Community Advisor
Madalyn_DestafneyCommunity AdvisorAccepted solution
Community Advisor
November 17, 2023
If this helped you, please mark correct to help others : )
RandyRoberts
Community Advisor
Community Advisor
November 17, 2023

As Madelyn said, you can't block it but you could make it appear in bold Red if the Due date is within 2 weeks of the entry date, or you could set the formatting to go Red if the date is too soon after the predecessor date. In fact, you could make the entire row turn red so they actually notice it.