Yet another question! I'm finding that with cross-project predecessors, "update on change" does not automatically change (recalculate) successor task dates when dates on the predecessor tasks are changed. One has to manually recalculate the timeline or wait overnight. I want to be that this is working as intended. If so, I'm going to submit an idea that it be made so.
Thanks!
Topics help categorize Community content and increase your ability to discover relevant content.
Hi Jason,
Yep, As Designed, as I understand it; one of several reasons we created our Force Timeline solution, which provides a simple, schedulable way to automatically recalculate the timelines for all projects matching a selected filter, ensuring they are up to date.
Regards,
Doug
Ok, that's what I figured. Thanks for your help Doug!