Expand my Community achievements bar.

The Community Advisors application is now OPEN for the second class of 2024. Apply to become a part of this exclusive program!

Yet another question! I'm finding that with cross-..

Avatar

Level 2

Yet another question! I'm finding that with cross-project predecessors, "update on change" does not automatically change (recalculate) successor task dates when dates on the predecessor tasks are changed. One has to manually recalculate the timeline or wait overnight. I want to be that this is working as intended. If so, I'm going to submit an idea that it be made so.

Thanks!

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 10

Hi Jason,

Yep, As Designed, as I understand it; one of several reasons we created our Force Timeline solution, which provides a simple, schedulable way to automatically recalculate the timelines for all projects matching a selected filter, ensuring they are up to date.

Regards,

Doug