Expand my Community achievements bar.

The Community Ideas review for H1 2025 is out now, see which ideas our Product team prioritized and let us know your thoughts.

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

Why would my due dates be different on two projects with the same start date, task constraints, and duration type?

Avatar

Level 3
 
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

3 Replies

Avatar

Level 2

‚Check the Project Owners and the project settings to see if you have incorporated Weekends / Holidays in the set up.

Avatar

Level 4

It is possible that an assignee is on holiday, as registered in the Workfront calendar, and that therefore the planned end date of the task has been pushed further.

Avatar

Level 4

The above two comments are true and also IF the planned hours and/or planned start TIME isn't the same on all on both project or the tasks within them, it could throw off the planned completion date.