Weekend due dates

Avatar

Level 2

Is there a way to make a project include weekends in the timeline so that tasks can be due on the weekend for that project only? Or this a global setting for all projects?

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 7

Hi Lynda,

The project schedule is based on the schedule that's associated with the individual project so you can create a custom schedule that includes weekends if you'd like. There's more information here.

Hope this helps,

Teale

View solution in original post

2 Replies

Avatar

Correct answer by
Level 7

Hi Lynda,

The project schedule is based on the schedule that's associated with the individual project so you can create a custom schedule that includes weekends if you'd like. There's more information here.

Hope this helps,

Teale