Using a Backlog portfolio to store waterfall projects for later consideration.
We have the following high-level annual project portfolio planning steps:
1) Requestor submits request
2) Requestor's manager approves/or declines the request
3) For approved requests, the portfolio manager converts the request to a project
4) Collectively, the projects are discussed at the Steering committee
5) The Steering committee selects one of the following for Projects activities are the following:
a) Approved to move forward
b) Declined
c) Held for additional information
d) Moved to the backlog
The part of the process not working well is pulling projects out of the backlog. It appears that once they're converted to a project, there's no option to resurrect them as a request and go back through the approval process.
The question is, can a project be turned back into just a request or are there any other suggestions to have the requester be able to pull it out of a project backlog, make desired changes and resubmit the request after it's been converted to a project?