user assigned to task available hours

  • March 22, 2023
  • 1 reply
  • 1110 views

is there a way to have a task report that when it pulls in the current user assigned to that task, it display how many hours they might have for the day?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by CynthiaBoon

Have you looked into using any of WF's resource management tools like Workload Balancer, Planner or Utilization tools? You can pull multiple teams/users into these and see what they're assigned to and be able to check their planned hours/due dates/etc so you're not overbooking resources. I recommend the Workload Balancer.
There's a great overview article on these here with links to more specifics within.

@cynthiaboon I was looking for the recording of the very recent webinar all about the resource management tools, can you help me locate and post here?


Absolutely!!  Here's the link with the recording and the presentation.  Thanks for tagging me in!

 

 March 2nd [Event Follow-up] Navigating the Resource Management Toolset 

1 reply

Madalyn_Destafney
Community Advisor
Community Advisor
March 23, 2023

Hi there, are you asking for the planned hours for those tasks to also show in your task report? If so, you can add the task planned hours as a column...not quite sure what you're asking, can you clarify?

If this helped you, please mark correct to help others : )
flieckster
Level 2
March 23, 2023

I am a PM, that shares design and writer resources with other PM's, when i'm looking at a task that is assigned to a writer, i'd like to see how many available hours that person might have left in their capacity for that day regardless of the task i have assigned to them. The issue is, with several PM's using the same resources, we end up moving a task, and over loading the design/writer resource, and you can't see that overload unless you are refreshing the workload tool constantly. it would be easier if it was built in to projects to see if that person is overloaded at a glance. 

CynthiaBoon
Adobe Employee
CynthiaBoonAdobe EmployeeAccepted solution
Adobe Employee
March 23, 2023

Have you looked into using any of WF's resource management tools like Workload Balancer, Planner or Utilization tools? You can pull multiple teams/users into these and see what they're assigned to and be able to check their planned hours/due dates/etc so you're not overbooking resources. I recommend the Workload Balancer.
There's a great overview article on these here with links to more specifics within.

@cynthiaboon I was looking for the recording of the very recent webinar all about the resource management tools, can you help me locate and post here?


Absolutely!!  Here's the link with the recording and the presentation.  Thanks for tagging me in!

 

 March 2nd [Event Follow-up] Navigating the Resource Management Toolset