Update Parent Task Status, do not allow subtasks control the parent task status | Community
Skip to main content
May 16, 2024
Solved

Update Parent Task Status, do not allow subtasks control the parent task status

  • May 16, 2024
  • 1 reply
  • 973 views

How can I make updates to the parent task status?

 

Currently, I can not make updates to the parent task status since there are subtasks. I am getting the error, "this field is automatically calculated by the system". I am want to be able to manually make updates to parent task status even when there are subtasks. 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by skyehansen

According to this article https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/projects/update-work-on-a-project/update-task-status "You can update the Status of a parent task to Complete when the Summary Completion Mode of the project is set to Manual and the subtasks are completed or incomplete."

1 reply

skyehansen
Community Advisor
skyehansenCommunity AdvisorAccepted solution
Community Advisor
May 19, 2024

According to this article https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/projects/update-work-on-a-project/update-task-status "You can update the Status of a parent task to Complete when the Summary Completion Mode of the project is set to Manual and the subtasks are completed or incomplete."

May 20, 2024

Where can I update  Summary Completion Mode? I do not want to update the parent task to complete manually, I want to update to another status

skyehansen
Community Advisor
Community Advisor
May 20, 2024

update it on the project. (edit the project and scroll down)