Hi everyone -
I'm hoping someone can help me understand task tracking mode. I'm running a pilot where we're looking to revamp some projects to include "catch-all" tasks. They will not be resolved after finishing one task, but used for multiple needs over the course of a month, to be resolved at month's end.
I'm changing some of the task's modes from "user must update" to "auto-complete." From what I understand, the tasks should complete at due date except if it has a predecessor which is incomplete. The tasks I'm using have no predecessors and a due date of last business day of month/ 5:00p.m. For some reason, I cannot get tasks to auto close no matter what I do.
Is there something I'm missing?