Expand my Community achievements bar.

SOLVED

Timesheet hours populate in projects?

Avatar

Level 2

When a user populates hours for tasks on their timesheet, are those hours then automatically reflected on task hours in the given projects?  Thank you

1 Accepted Solution

Avatar

Correct answer by
Level 4

Hello @keri13 

I have just tested this to make sure and they do automatically add the hours to a task from a time sheet. 

You don't even have to close it just adding the hours in will do the job. 

Scott_Goodwin_0-1708504086369.png

Scott_Goodwin_1-1708504121268.png

This also shows at task and project level.

If your happy please mark this as the accepted solution for others to find. Thank you

View solution in original post

2 Replies

Avatar

Correct answer by
Level 4

Hello @keri13 

I have just tested this to make sure and they do automatically add the hours to a task from a time sheet. 

You don't even have to close it just adding the hours in will do the job. 

Scott_Goodwin_0-1708504086369.png

Scott_Goodwin_1-1708504121268.png

This also shows at task and project level.

If your happy please mark this as the accepted solution for others to find. Thank you