Hi Yolanda,
The first thing I would check is what 'completion mode' has been selected within the project settings. When it's set to automatic, project status will automatically change to closed when the overall percent complete is 100%. If it's set to manual, the Project owner would always have to manually change the status to closed.
If the completion mode is set to automatic and the status is still not changing, it's likley that you have some open issues or outstanding approvals on your tasks within the project.