Task report with chart of task completed prior to the completion date compared to past the completion date

  • November 2, 2022
  • 1 reply
  • 462 views

Any ideas on how to set up a simple report using a chart option of either the number or percentage of tasks completed by the planned completion date compared to those completed after the planned completion date.  I can't seem to set the report up correctly to get the data I want on a chart.  Thanks!

Best answer by Doug_Den_Hoed__AtAppStore

 

Hi @suzyf,

 

I suggest you group by Task Progress (e.g. On Time, At Risk, Behind, Late), then chart as you see fit (e.g. Pie Chart, Stacked Column over time, etc.) .

 

Regards,

Doug

1 reply

Doug_Den_Hoed__AtAppStore
Community Advisor
Doug_Den_Hoed__AtAppStoreCommunity AdvisorAccepted solution
Community Advisor
November 2, 2022

 

Hi @suzyf,

 

I suggest you group by Task Progress (e.g. On Time, At Risk, Behind, Late), then chart as you see fit (e.g. Pie Chart, Stacked Column over time, etc.) .

 

Regards,

Doug