Greetings!

 

I'm looking to include in my report the following:

  1. Tasks assigned to $$USER.ID
  2. Predecessor Is Complete - True
  3. Project Status - In Progress
  4. Task Percent Complete - Not Equal to 100%
  5. Task is Not equal to Complete, Canceled or On Hold
  6. Tasks with no predecessors - How do I include this one in my report? I'm not figuring this one out. 

Thank You, Deb

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by KellieGardner

Hi Deb -

 

You'll want to use the filter "can start" = True. This will pull in anything that is ready to start - meaning it has predecessors complete or does not have an dependencies.

 

 

2 replies

Richard__Carlson
Community Advisor
Community Advisor
March 20, 2024

In order to make things consistent and simple we have our users utilizing the new home and specifically the My Tasks widget, I am just curious if you have tried using this tool and how it might have potentially fallen short of your needs.

KellieGardner
Community Advisor
KellieGardnerCommunity AdvisorAccepted solution
Community Advisor
March 20, 2024

Hi Deb -

 

You'll want to use the filter "can start" = True. This will pull in anything that is ready to start - meaning it has predecessors complete or does not have an dependencies.

 

 

DeborahLeigh123
March 20, 2024

Perfect. Many thanks!