Expand my Community achievements bar.

Join us LIVE in San Francisco on November 14th for Experience Makers The Skill Exchange. Don't miss out on this free learning event!
SOLVED

Task report splitting out planned hours by assignee

Avatar

Level 10

Hi WF Community,

Does anyone know if it's possible to split out a task report by user and planned hours, or would an assignment or work item report be the only options for that?

Example:

- 20 planned hours on Task A

- Pardeep is assigned 5 planned hours

- Keleel is assigned 15 planned hours

 

We would like to see the task report grouped by task, and then see the breakout of planned hours by assignee under the task.

I know this can be handled in an assignment report, but curious if a task report can do this as well?
Thanks,
Nick

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

hi Nick, I'm not sure if you're familiar with collections in reporting, but if you are, your question is an example of where they would be used. 

https://experienceleague.adobe.com/docs/workfront/using/reporting/reports/text-mode/reference-collec...

 

You're specifically looking for the assignments collection and then Planned Hours is known as workRequired in the system. A quick search focusing on collections, assignments and workrequired would definitely net you with some good samples to start experimenting with.

https://experienceleaguecommunities.adobe.com/t5/custom/page/page-id/GlobalSearch#q=collections%20re...

 

Here's a very specific answer with that in mind: https://experienceleaguecommunities.adobe.com/t5/workfront-questions/text-code-for-assignement-break...

View solution in original post

9 Replies

Avatar

Correct answer by
Community Advisor

hi Nick, I'm not sure if you're familiar with collections in reporting, but if you are, your question is an example of where they would be used. 

https://experienceleague.adobe.com/docs/workfront/using/reporting/reports/text-mode/reference-collec...

 

You're specifically looking for the assignments collection and then Planned Hours is known as workRequired in the system. A quick search focusing on collections, assignments and workrequired would definitely net you with some good samples to start experimenting with.

https://experienceleaguecommunities.adobe.com/t5/custom/page/page-id/GlobalSearch#q=collections%20re...

 

Here's a very specific answer with that in mind: https://experienceleaguecommunities.adobe.com/t5/workfront-questions/text-code-for-assignement-break...

Avatar

Level 10

Thanks for nudging me in that direction, Skye.  A collection could work, I'll see if it suffices based on requirements.  I was able to list assignees and their planned hours in a custom column.

Avatar

Level 1

Hi @NickVa1 were you able to find a solution? Keen to know as I'm trying to build a report to compare planned hours vs actual hours by job role/user. So far it seems I need to use an assignment report but this comes with some issues so was wondering if I could use a task report as well. 

 

Thanks

 

Mo

Avatar

Level 10

Hi Mo,
We're still determining which option works best for us, based on data points (fields) we want to include in the report that live on various objects.  There are limitations with each type of report (tasks, assignments, hours), depending on what data you want to see, and how you want it displayed.

  • An assignments report is nice if you just want to see assignment related data broken out by assignee (assuming you have multiple assignees assigned to a task).  Planned hours is easy to see by assignee.
  • If you want to see planned hours broken out by assignee on a task report, I had to create a custom calculated column, with the following text mode:
    • displayname=Planned HRS by Assignee
      listdelimiter=<p>
      listmethod=nested(assignments).lists
      textmode=true
      type=iterate
      valueexpression=CONCAT({assignedTo}.{name}," (",ROUND({workRequired}/60,2)," HRS",") ")
      valueformat=HTML
    • This is what the end result looks like:
      • Screenshot 2023-08-02 at 10.35.31 AM.png
  • An hours report shows too much duplicated data points if you're not aggregating/grouping data.

Hope that helps.

Avatar

Level 1

Hi Nick,

 

Thanks for sharing that view and text mode. Being able to break down planned hours by assignee on a task report it's definitely useful. Could you please also share the code for 'actual/planned hours' and 'remaining planned hours' column assuming it was both done using text mode?

Have you also looked into showing planned vs actual hours by job role? I have noticed with a task report, to get the variance or percentage of burn by job role accurately, you will need to have separate tasks for each user/job role (due to primary task owner). Not sure if there is a way to show this accurately on a report without separating task for each job role for tasks that currently have multiple assignments. 

 

Thanks


Mo

Avatar

Level 10

Hey Mo!

Here's the text mode for the "Actual/ Planned Hours" calculated custom column:

displayname=Actual/ Planned Hours
linkedname=direct
namekey=actualworkrequired
querysort=actualWork
textmode=true
valueexpression=CONCAT({actualWorkRequired}/60,' / ',{workRequired}/60)
valuefield=actualWorkRequired
valueformat=compound
viewalias=actualworkrequired

 

Here's the text mode for the "Remaining Planned Hours" calculated custom column:

aggregator.valueexpression=SUB({workRequired}, {actualWork})
aggregator.valueformat=compound
displayname=Remaining Planned Hours
linkedname=direct
textmode=true
valueexpression=SUB({workRequired}, {actualWork})/60
valueformat=customNumberAsString

 

Unfortunately, grouping by job role, on a task report, only allows you to do this by the primary assignee.  This means that if you have many assignees on one task, it will only look at the primary assignee.

Avatar

Level 4

Hi Nick, I used the below code on a Task report which provides this display. Do you know what the code would be to pull this same display on an Assignments report?

displayname=Assignee Planned Hrs
listdelimiter=<p>
listmethod=nested(assignments).lists
textmode=true
type=iterate
valueexpression=CONCAT({assignedTo}.{name}," (",ROUND({workRequired}/60,2)," Hrs",") ")
valueformat=HTML

 

jamesmillerzjd_1-1695315674480.png

 

 

Avatar

Level 10

Hi jamesmiller-zjd,

If you want to see the planned hours by assignee on an assignment report, you won't need text mode.  
If you group by task name (or better, task ID since that's more unique), it doesn't matter if you have one or many assignees on the task, it will break out their planned hours for each assignee on separate rows.  Getting accurate actual hours per assignee is the tough part I was unable to accomplish using an assignment report.

For tasks that have multiple assignees, to get both planned and actual hours per assignee on separate rows in the report, I used a Work Item report.

  • Here's the assignee planned hours text mode:
    • aggregator.displayformat=minutesAsHoursString
      aggregator.function=SUM
      aggregator.namekey=view.relatedcolumn
      aggregator.namekeyargkey.0=assignment
      aggregator.namekeyargkey.1=workRequired
      aggregator.valuefield=assignment:workRequired
      aggregator.valueformat=compound
      displayname=Assignee Planned Hrs
      linkedname=assignment
      namekey=view.relatedcolumn
      namekeyargkey.0=assignment
      namekeyargkey.1=workRequired
      querysort=assignment:workRequired
      textmode=false
      valuefield=assignment:workRequired
      valueformat=compound
      viewalias=assignment:workrequired
  • Here's the assignee actual hours text mode:
    • aggregator.displayformat=minutesAsHoursString
      aggregator.function=SUM
      aggregator.namekey=view.relatedcolumn
      aggregator.namekeyargkey.0=assignment
      aggregator.namekeyargkey.1=actualWorkCompleted
      aggregator.valuefield=assignment:actualWorkCompleted
      aggregator.valueformat=compound
      displayname=Assignee Actual Hrs
      textmode=true
      valueexpression={assignment}.{actualWorkCompleted}/60
      valueformat=doubleAsDouble
  • And, if you want the variance between the two, here's the text mode for that:
    • aggregator.function=SUM
      aggregator.valueexpression=({assignment}.{workRequired}-{assignment}.{actualWorkCompleted})/60
      aggregator.valueformat=compound
      displayname=Remaining Hrs
      textmode=true
      valueexpression=({assignment}.{workRequired}-{assignment}.{actualWorkCompleted})/60
      valueformat=doubleAsDouble
  • You'll want to group by something (e.g. task, planned completion date, etc.)

 

Hope that helps!
Nick