Task report: how to add information on other tasks from the same project | Community
Skip to main content
Level 4
June 7, 2022
Solved

Task report: how to add information on other tasks from the same project

  • June 7, 2022
  • 1 reply
  • 521 views

Hi there,

We have a task report that filters projects for one specific task (pre-commercial task = in progress).

Now, we would like to add information to that task report in a column that will give us the end date of another task (commercial launch) in that same project.

Any ideas on how to achieve this?

Any help is appreciated :).

Thank you!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Jason_JB

It’s not exactly what I think you’re asking for, but a workaround we’re using is for Fusion to replicate/calculate a few key task dates to a custom field on the project. (Like a project’s golive)

on a task level we also have a custom field where it looks at the number of days different that task is from another task (with a specific attribute).

1 reply

Jason_JB
Jason_JBAccepted solution
Level 5
June 7, 2022

It’s not exactly what I think you’re asking for, but a workaround we’re using is for Fusion to replicate/calculate a few key task dates to a custom field on the project. (Like a project’s golive)

on a task level we also have a custom field where it looks at the number of days different that task is from another task (with a specific attribute).