We have a task report that filters projects for one specific task (pre-commercial task = in progress).
Now, we would like to add information to that task report in a column that will give us the end date of another task (commercial launch) in that same project.
It’s not exactly what I think you’re asking for, but a workaround we’re using is for Fusion to replicate/calculate a few key task dates to a custom field on the project. (Like a project’s golive)
on a task level we also have a custom field where it looks at the number of days different that task is from another task (with a specific attribute).
It’s not exactly what I think you’re asking for, but a workaround we’re using is for Fusion to replicate/calculate a few key task dates to a custom field on the project. (Like a project’s golive)
on a task level we also have a custom field where it looks at the number of days different that task is from another task (with a specific attribute).