Expand my Community achievements bar.

Interested in getting an Adobe Workfront certification? Don't miss our AMA on June 10th, where our experts will be available to answer any questions you may have about getting certified!

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

SOLVED

Task report: how to add information on other tasks from the same project

Avatar

Level 4

Hi there,

We have a task report that filters projects for one specific task (pre-commercial task = in progress).

Now, we would like to add information to that task report in a column that will give us the end date of another task (commercial launch) in that same project.

Any ideas on how to achieve this?

Any help is appreciated :).

Thank you!

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 7

It’s not exactly what I think you’re asking for, but a workaround we’re using is for Fusion to replicate/calculate a few key task dates to a custom field on the project. (Like a project’s golive)

on a task level we also have a custom field where it looks at the number of days different that task is from another task (with a specific attribute).

View solution in original post

1 Reply

Avatar

Correct answer by
Level 7

It’s not exactly what I think you’re asking for, but a workaround we’re using is for Fusion to replicate/calculate a few key task dates to a custom field on the project. (Like a project’s golive)

on a task level we also have a custom field where it looks at the number of days different that task is from another task (with a specific attribute).