Task Numbers on Project Timeline Export (PDF/Excel)

  • June 10, 2024
  • 1 reply
  • 679 views

Hello,

 

When exporting a project timeline, the task number column is not included on the exported document. This occurs in both PDF and Excel formats. Does anyone know how to add this column to the export?

Best answer by Madalyn_Destafney

That can be annoying. What I suggest is temporarily adding a column into your Task View in the project to add task number, then do the export.

 

1 reply

Madalyn_Destafney
Community Advisor
Madalyn_DestafneyCommunity AdvisorAccepted solution
Community Advisor
June 10, 2024

That can be annoying. What I suggest is temporarily adding a column into your Task View in the project to add task number, then do the export.

 

If this helped you, please mark correct to help others : )