Task Assignee Permissions
I have a question from our stakeholders with what contribute access permission options are available for task assignees within a project. Specifically, they want their teams to be able to edit their assigned task status, but NOT the actual start/end dates of their assigned tasks. Is there a toggle for that? I don't see anything in regards to the actual start dates, I've already run down the list. I've toggled everything off except for Change Status, which inherently enables the ability to edit actual start/end dates. They seem to recall it working this way in the past, and maybe it, did but I don't see how to get it to that state anyway.
The "also grant...access to this project" hidden but the options is indeed set to View. So it's not that.