task actual durations | Community
Skip to main content
KristenS_WF
Level 6
August 29, 2022
Question

task actual durations

  • August 29, 2022
  • 2 replies
  • 952 views

Hi All,

 

Next month we're going to be conducting a review of some of our templates to determine if they need adjustments before we start launching our 2023-release projects.

 

I created a report that shows task Planned Duration, Actual Duration, and a calculated field showing the difference (in week days) between the Planned Start Date and Actual Completion Date.  When running my report, I noticed something curious with the Actual Duration data.

 

For example, I've got a task with a Planned Start Date of 1/20/22, a Planned Completion Date of 2/3/22, and an Actual Completion Date of 2/16/22.  The Planned Duration is 10 days, and my calculated field yields 19 days.  However, the Actual Duration shows 0 days.  When I take a look at the task details, the Actual Start Date and Actual Completion Date show identical date/time values.

 

Is this because the user simply marked the task complete without any additional steps?  Does the user have to click on Work On It to start the clock prior to completing the task in order for the Actual Duration field to reflect meaningful data?

 

Thanks.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

August 29, 2022

Someone probably left the status as new and went straight to complete, without putting the job in progress first.

KellieGardner
Community Advisor
Community Advisor
August 30, 2022

I concur with Stacey. It's likely that the user went strait from new to complete. 

RandyRoberts
Community Advisor
Community Advisor
March 1, 2023

Maybe comparing the handoff date to the actual Complete Date would be more accurate?