Successor task Start On date based on actual completion date of the predecessor?

  • February 12, 2021
  • 1 reply
  • 649 views

We have a project where a form is sent out with the hope it will be returned quickly. If not, reminders are sent at 2 months, 4 months, and 6 months after. Once the form is returned, there are processing tasks that need to be completed.

We want the processing tasks to start when any of the follow-ups are actually completed. We’ve tried different combinations of task constrains and predecessors but the Start On is calculated from the planned completion dates of the tasks.

Any suggestions? Thank you.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Doug_Den_Hoed__AtAppStore

Hi Kathy,

Your requirements remind me of our As Soon As Impossible blog post, which focuses on "accelerating" a Project plan by setting dependent Task Planned Start Dates to match their Handoff Dates, which get filled in once their Predecessors Actual Completion Date(s) appear (the Handoff Date matching that same Actual Completion Date, "handing off" the momentum of the Project completion to that dependent Task.

In your case, the norm is that the Predecessors (i.e. the Tasks that track the Custom Forms coming back) are late, so you'd then be moving the dependent Task's Planned Completion Date "out", but the concept is the same. You could do so manually, by reporting on those (such) dependent Tasks whose Handoff Date is Not Blank and does not match its Planned Start Date and then copy/pasting the Handoff Date into the Planned Start Date; or if there's enough data that it's warranted, automate that update using (for example) our UberCalc solution.

Regards,

Doug

1 reply

Doug_Den_Hoed__AtAppStore
Community Advisor
Doug_Den_Hoed__AtAppStoreCommunity AdvisorAccepted solution
Community Advisor
February 12, 2021

Hi Kathy,

Your requirements remind me of our As Soon As Impossible blog post, which focuses on "accelerating" a Project plan by setting dependent Task Planned Start Dates to match their Handoff Dates, which get filled in once their Predecessors Actual Completion Date(s) appear (the Handoff Date matching that same Actual Completion Date, "handing off" the momentum of the Project completion to that dependent Task.

In your case, the norm is that the Predecessors (i.e. the Tasks that track the Custom Forms coming back) are late, so you'd then be moving the dependent Task's Planned Completion Date "out", but the concept is the same. You could do so manually, by reporting on those (such) dependent Tasks whose Handoff Date is Not Blank and does not match its Planned Start Date and then copy/pasting the Handoff Date into the Planned Start Date; or if there's enough data that it's warranted, automate that update using (for example) our UberCalc solution.

Regards,

Doug

KAM30Author
Level 3
February 13, 2021

I like your idea of the report. Thanks Doug for the explanation. I appreciate the help!