Successor task Start On date based on actual completion date of the predecessor?
We have a project where a form is sent out with the hope it will be returned quickly. If not, reminders are sent at 2 months, 4 months, and 6 months after. Once the form is returned, there are processing tasks that need to be completed.
We want the processing tasks to start when any of the follow-ups are actually completed. We’ve tried different combinations of task constrains and predecessors but the Start On is calculated from the planned completion dates of the tasks.
Any suggestions? Thank you.