is it possible to make a report for different tasks in different projects? if i want to report on task 20 in project a, task 1 in project b, task 55 in project c and task 16 in project d

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Richard_Le_

Hi Michelle,

You could attach a custom form to the tasks that you want to report on which has a simple tickbox field. You would then simply create a task report and filter based on this custom field.

I often do this where I want to surface particular tasks to execs in my reports. I created a field called 'executive interest' and when it is ticked on certain tasks, these tasks automatically pull into my task report and are visible to the senior leadership team.

Best Regards,

Rich.

1 reply

Richard_Le_Community AdvisorAccepted solution
Community Advisor
March 18, 2021

Hi Michelle,

You could attach a custom form to the tasks that you want to report on which has a simple tickbox field. You would then simply create a task report and filter based on this custom field.

I often do this where I want to surface particular tasks to execs in my reports. I created a field called 'executive interest' and when it is ticked on certain tasks, these tasks automatically pull into my task report and are visible to the senior leadership team.

Best Regards,

Rich.