Solution for 0 Day Duration + Planned Cost?
We have recently started using the planned cost function in Workfront. Previously we managed our costs by managing labor hours (planned hours) but with the increase in leveraging software or off/nearshoring we had to get more mature in using planned cost.
We set some tasks at a 0-day duration with an "ASAP" constraint to make sure they are done on the same day as their predecessor but are also connected and moving with the predecessor during project adjustments, but that 0day duration zeroes out planned costs.
I GET that a task cannot actually have a 0-day duration, but is there an alternate solution to have a task after a predecessor due on the same day AND will move out if you move the preceding task? My best idea so far is to use a duration in the increment of hours so that I can keep "ASAP as the task constraint and have it trigger immediately.