How to link risks to tasks within a project plan

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Doug_Den_Hoed__AtAppStore

 

Hi @aswi,

 

Since the native Risk object does not (yet) support custom data and is only available at the Project level (where you're interested in Task level), one common approach is to instead use the native Issue object instead (and as there are four built in, you could rename one to "Risk", if you wish).

 

Regards,

Doug 

1 reply

Doug_Den_Hoed__AtAppStore
Community Advisor
Doug_Den_Hoed__AtAppStoreCommunity AdvisorAccepted solution
Community Advisor
April 7, 2023

 

Hi @aswi,

 

Since the native Risk object does not (yet) support custom data and is only available at the Project level (where you're interested in Task level), one common approach is to instead use the native Issue object instead (and as there are four built in, you could rename one to "Risk", if you wish).

 

Regards,

Doug