Question
Resource Planner: Confusion with Available Hours
Hi everyone, Apologies for inundating the Community with all of my resourcing questions, really pushing hard to get this off the ground on our team! Am I crazy or did the Available Hours column in the Resource Planner used to refer to the number of hours that were available to be budgeted/scheduled after the planned hours had been subtracted out? You were then able re-prioritize the projects so that the highest priority projects had first dibs on the pool of available hours. I remember seeing this in the Ascent training videos... I guess I'm not understanding what the point of showing 40 available hours per user is? I'd much rather see:
(40 hrs) - (all planned hours on various tasks) = Available Hours
so that I know what's available to be budgeted to that resource/project, but maybe I'm not thinking about this correctly? Thank you! Christine Zhu Chobani