Resource Planned Hours by Projected Task Start and End Dates

Avatar

Level 1

Is there a way to view the planned hours for resources in either the Resource Planner or Workload Balancer by the projected start and end dates of a task?

Currently, we manually update the planned start and end dates of tasks in our projects to get an accurate view of resource availability, as our task dates often get delayed or shift for various reasons.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Community Advisor

In Workload Balancer, you can show the projected dates.

 

KellieGardner_0-1749768660455.png

 




Avatar

Administrator

@zac2016 just checking in! Were you able to get this resolved? If one of the replies above helped—whether it completely solved the issue or simply pointed you in the right direction—marking it as accepted can make it much easier for others with the same question to find a solution. And if you found a different way to fix it, sharing your approach would be a great contribution to the community. Your follow-up not only helps close the loop but also ensures others benefit from your experience. Thanks so much for being part of the conversation!



Kautuk Sahni